Status of Major Gas Pipeline Projects in India

Given below is the status of ongoing gas pipeline projects in India. The table was updated on December 20, 2011.

S. No. Name Of The Pipeline Company Expected Time Of Completion Length(in Kms) Cost ( in Rs.Million)
1 Chainsa-Gurgaon-Jhajjar-Hisar Gail (India) Ltd 2011 450 12500
2 Dadri-Bawana-Nangal Gail (India) Ltd 2011 610 22000
3 Kochi-Kanjirkkod-Bangalore Gail (India) Ltd 2013 1114 30320
4 Jagdishpur-Haldia Gail (India) Ltd 2013-2014 2050 76000
5 Dabhol-Bangalore Gail (India) Ltd 2012-2013 1389 45430
6 Kakinada-Vasudebpur-Howrah Relogistics  Infrastructure Ltd 2012-2013 1100 NA
7 Kakinada-Vijaywada-Nellore-Chennai Relogistics  Infrastructure Ltd 2012-2013 600 NA
8 Chennai-Tuticorin Relogistics  Infrastructure Ltd 2012-2013 670 NA
9 Chennai-Bangalore-Mangalore Relogistics  Infrastructure Ltd 2012-2013 660 67960
10 DVPL – GREP Upgradation Gail (India) Ltd 2011 NA NA
11 Mallavaram-Bhopal-Bhiwara-Vijaypur Gujarat State Petronet Ltd 2014 1585 72570
12 Mehsana-Bhatinda Gujarat State Petronet Ltd 2014 1670
13 Bhatinda-Jammu-Srinagar Gujarat State Petronet Ltd 2014 740 64490

 